| University | Te Aho o Te Kura Pounamu (Te Kura) |
| Subject | AS 91576 Mathematics and Statistics 3.4: Critical Path Analysis |
MXO3042Y1 Critical Path Analysis Assessment: Quiz Evening Report (NCEA Level 3, AS 91576)
| Activity | MXO3042Y1 internal assessment activity |
| Provider | Te Aho o Te Kura Pounamu (Te Kura) |
| Standard | Achievement Standard 91576 (version 2), Mathematics and Statistics 3.4 – Use critical path analysis in solving problems |
| Level / credits | NCEA Level 3, internal, 2 credits |
| Conditions | Open book, supervised, no time limit (allow at least one hour) |
This Te Kura NCEA Level 3 maths activity asks you to write a report for a parents’ committee planning a quiz evening to fund a netball team’s trip. Using the task list, durations and precedences in Resource A, you draw a network diagram, find the critical path and earliest finish, schedule every task, allocate the work to the fewest committee members and then test the plan against an unexpected delay and a missing member.
Assessment Criteria
- Achieved: apply critical path analysis in solving problems.
- Merit: apply critical path analysis, using relational thinking, in solving problems.
- Excellence: apply critical path analysis, using extended abstract thinking, in solving problems.
Resource A: Project Tasks
| Task | Description | Weeks | Precedence |
| A | Set a date for the quiz evening | 1 | – |
| B | Book a venue | 1 | A |
| C | Advertise the quiz evening and sell tickets | 4 | A, B |
| D | Find a suitable person to be the quiz master | 2 | A |
| E | Write the questions and answers | 4 | A |
| F | Check the answers | 1 | A, E |
| G | Print out recording sheets for writing down the answers | 1 | A, E, F |
| H | Organise the food and drink | 2 | A, B |
| I | Seek donated goods for prizes | 4 | A |
| J | Set up the venue on the day of the quiz | 1 | A, B, C, D, E, F, G, H, I |
Introduction: The Quiz Evening
A small committee of parents is planning a quiz evening to raise funds for a team of netball players to travel to a national tournament. As well as selling tickets, they will sell food and drinks on the night and hope to collect prizes donated by local people and businesses. The times given are the number of weeks leading up to the quiz evening, and committee members work on the tasks in their spare time. The quality of your report and how well you link your findings to this context, including the implications of unexpected delays, determine the overall grade. Clearly communicate the different parts of your report, including any diagrams.
Task 1
Use the information in Resource A to prepare a report for the organisers of the quiz evening and recommend how the tasks could be allocated to a minimum number of committee members. The report should include:
- a network diagram showing all the tasks in the project
- the tasks in the critical path
- the minimum length of time required to complete all the tasks
- the start and finish time for each task.
Assume that all committee members will set the date (Task A) and help set up the venue (Task J), and that a different member from the person who wrote the questions will check the answers.
Task 2
If the committee member writing the questions has an unexpected illness and there is a two-week delay in writing the questions (Task E), discuss the impact of this delay on the planning and suggest a way the committee could overcome the problem and still be ready for the quiz evening.
If one committee member is unavailable and the committee has one less member, find the minimum number of weeks it would take to complete the organisation and show how the tasks could be reallocated.
Your overall grade is determined by the quality of your reasoning and how well you link it to the context.
need help with your 91576 critical path analysis report?
Hire NZ Native Experts 24/7.
Many Year 13 students can find the critical path for the quiz evening but stop there, which only reaches Achieved. Merit and Excellence in AS 91576 depend on linking every number to the committee: using float to share tasks fairly, showing a clear Gantt-style schedule, and explaining exactly how the two-week delay to Task E and the loss of one member change the finish time and the allocation. Our NCEA maths assignment help can guide your network diagram and reasoning, and our homework help for senior students supports clear report writing. You can also see how scheduling is applied in the SARC321 Gantt and site logistics assignment. For a worked structure, see our AS 91576 critical path quiz evening sample (for reference only) and the guide on how to approach AS 91576 critical path analysis.
- LAWCOMM 785 Patent Practice Assignment 2026: Letter of Advice on Challenging eVTOL Patent Applications in NZ and Australia | University of Auckland
- MGMT902 Enterprise and Information Systems Assignment 2: Cyber Security Governance and ICT Strategy Report | AIS
- Managing for Sustainability Assessment 1 Report and Academic Poster 2026 | Otago Polytechnic
- SCIE707 Research Project Proposal and Cultural Safety & Engagement Statement Assessment 2026 | AUT
- CA ANZ Tax (NZ) Assessment 1 Case Study Term 4 2026: Hume & Hearth Ceramics Limited
- BILD 361 Project Management Assessment 2, 2026: BIM Residential Project Management Plan | VUW
- SARC 321 Construction Assignment 3 2026: Envelope, Gantt Chart and Site Logistics Plan | Victoria University of Wellington
- LAWCOMM 782 Trade Mark Practice Letter of Advice 2026 | University of Auckland
- LAWCOMM 795 Copyright and Design Final Assessment 2026 | University of Auckland
- BSNS5202 Advanced Business Information Assessment 3, 2026 | Open Polytechnic